The Mexico City Council tackled a hefty agenda at the Nov. 10 meeting that included updates to public works projects and discussion of budgeted expenses.
The meeting began with the establishment …
This item is available in full to subscribers.
We have recently launched a new and improved website. To continue reading, you will need to either log into your subscriber account, or purchase a new subscription.
If you are a digital subscriber with an active subscription, or you are a print subscriber who had access to our previous website, then you already have an account here. Just reset your password if you have not yet logged in to your account on this new site.
If you are a current print subscriber and did not have a user account on our previous website, you can set up a free website account by clicking here.
Otherwise, click here to view your options for subscribing.
Please log in to continue |
The Mexico City Council tackled a hefty agenda at the Nov. 10 meeting that included updates to public works projects and discussion of budgeted expenses.
The meeting began with the establishment of filing dates for the 2026 municipal election, which will be held on April 7. There will be two three-year terms available and statements of candidacy will be accepted from Dec. 9-30.
Mayor Steve Haag and Council Member Larry Webber have terms that will expire.
The council also approved the annual contribution of $13,000 to the Mexico Area Chamber of Commerce to assist with marketing activities for the 2025-26 budget year.
Stormwater improvement projects will continue with the approval of a resolution authorizing the City of Mexico to accept temporary construction easements for the North Calhoun Street project.
According to Drew Williford, deputy city manager, this will likely be the last easement to be accepted for this project.
At the meeting, Williford also discussed two new developments in the North Kentucky Street stormwater improvement project requiring change orders. The first called for new drainage structures behind the curb and gutter on both the southern and eastern portions of the project.
“Near the Curtis Street intersection, we attempted to reuse some of the existing storm sewer that was in place and found that we could not do so,” Williford said.
There will be a total of 10 storm sewers in need of removal and replacement. Estimates for the project were provided by Rhad Baker Construction, which estimated $3,314 per structure, bringing the new cost up to $33,143.
The second change order called for the removal and replacement of an additional foot of pavement in order to cast the curb and gutter independently of the roadway.
Rhad Baker Construction provided an estimate of $47,491. Both change orders were forwarded to the Department of Natural Resources and are eligible for reimbursement under the ARPA stormwater grant.
New business also included a resolution authorizing the city manager to sign contract documents with Surdex Corporation for the 2025 Aerial Photography Project, which will cost $17,500.
Other purchases approved during staff reports were as follows: